A proper site visit stops surprise costs and keeps your event safe. At HireAnything we’ve audited hundreds of quotes and the pattern is clear: missing data leads to price spikes.
Why a Site Visit Matters
Legal Duty of Care
UK law requires a risk assessment for any temporary structure. The Health and Safety Executive expects a written record before erection. Without it you could breach the Consumer Rights Act 2015.
Cost Accuracy
Suppliers who skip the walk‑around often add £75‑£250 per day in contingency fees. A thorough visit locks the price early.
Ground & Surface Assessment
Soil Type & Load Bearing
Clay, chalk, sand – each behaves differently under a 3‑tonne frame. A simple penetrometer test tells you if you need ground plates or a ballast system.
Drainage & Water Table
Standing water after rain can undermine anchorage. Check the site 24 hours after a downpour; note any soft spots.
Access, Power & Services
Vehicle Access & Turning Circles
Measure the narrowest gate, low bridges and overhead cables. A 7.5 t lorry needs at least 3.5 m width and 4.5 m height clearance.
Electrical Supply & Generator Needs
Most marquees draw 10‑30 kW for lighting, heating and catering. Verify the nearest three‑phase point or budget a silent diesel generator at £120‑£180 per day.
Structural & Safety Compliance
Wind Loading & Anchorage
UK wind zones dictate the required ballast. In Zone 4 a 6 m span may need 2 t of water barrels per leg.
Fire Safety & Escape Routes
All structures over 30 m² must have two independent exits. Fire‑retardant fabric and a £5M public liability policy are non‑negotiable.
Quick Reference Checklist
- Confirm site address and postcode
- Record ground type and bearing capacity
- Check drainage after rain
- Measure access width, height and turning radius
- Identify nearest three‑phase power point
- Calculate required generator size
- Determine wind zone and ballast plan
- Verify fire‑exit layout and fabric rating
- Confirm £5M public liability insurance
- Note any local authority licensing requirements
- Agree on set‑up and dismantle windows
- Document all findings with photos
Ground Condition vs Marquee Type
| Ground | Suitable Marquee | Extra Ballast |
|---|---|---|
| Firm turf | Frame‑tented | None |
| Soft clay | Clear‑span with base plates | Water barrels |
| Sand / gravel | Pole‑tented with screw anchors | Sand bags |
| Concrete | Any – use weighted feet | Minimal |
Detailed UK Pricing Guide & Cost Breakdown
Typical Marquee Hire Rates (2024‑25)
Prices vary by region, season and specification, but the ranges below reflect what most reputable UK suppliers quote for a standard 3‑day hire (delivery, erection, dismantle and collection). All figures are exclusive of VAT.
- Clear‑span frame (3 m × 6 m) – 30 m²: £1,200 – £1,600
- Clear‑span frame (6 m × 12 m) – 72 m²: £2,800 – £3,600
- Clear‑span frame (9 m × 18 m) – 162 m²: £5,500 – £7,200
- Pole‑and‑canvas traditional marquee (4 m × 8 m): £1,500 – £2,100
- Luxury lined marquee (incl. carpet, chandeliers, climate control): add £1,200 – £2,500 on top of frame cost
Key Cost Drivers
- Ground conditions: Soft or sloping ground may require ground plates, ballast bags or a temporary sub‑base – typically £150 – £450 extra.
- Access restrictions: Narrow gates, low bridges or overhead cables can force a smaller vehicle or a crane lift – £200 – £600 surcharge.
- Power supply: If no three‑phase connection is within 30 m, a silent diesel generator (30 kW) costs £130 – £190 per day plus fuel.
- Heating & climate control: Gas patio heaters £30 – £55 each per day; electric heaters £25 – £40 each per day; full HVAC package £800 – £1,500 for a 3‑day event.
- Flooring: Interlocking timber deck £12 – £18 / m²; carpet tiles £8 – £12 / m²; raised dance floor £25 – £35 / m².
- Furniture & décor: Tables £12 – £18 each, chairs £3 – £6 each, linens £4 – £7 each, lighting packages £300 – £1,200.
- Insurance & permits: Public liability cover (usually £5 m) is often included; if the venue requires a separate event licence, budget £150 – £300.
Deposit & Payment Terms (Industry Standard)
- Deposit: 30 %– 50 % of the total quote, payable on confirmation. Non‑refundable if cancelled < 30 days before the event.
- Balance due: 7–14 days prior to delivery. Some suppliers accept staged payments (e.g., 50 % on booking, 25 % 30 days out, 25 % on day of erection).
- Cancellation policy:
- > 60 days: full refund of deposit.
- 30‑60 days: 50 % of deposit retained.
- < 30 days: full deposit forfeited; any incurred costs (e.g., custom flooring) also chargeable.
- Force majeure: Most contracts allow a re‑schedule within 12 months without penalty if the event is prohibited by government order.
UK Buyer Checklist & Legal Rights
Consumer Rights Act 2015 – What It Means for Marquee Hire
The Act treats a marquee hire as a service contract. The supplier must:
- Perform the service with reasonable care and skill (e.g., correct erection, safe anchoring).
- Complete the service within a reasonable time (agreed delivery/erection window).
- Provide the service as described in the quote (size, specification, accessories).
If any of these standards are not met, you are entitled to:
- Repeat performance (re‑erect or fix defects) at no extra cost.
- Price reduction (up to a full refund) if repeat performance is impossible or not done within a reasonable period.
- Claim damages for consequential loss (e.g., lost catering revenue) where the breach was foreseeable.
Pre‑Hire Verification Checklist
- Written quote & specification: Itemised list of marquee size, frame type, lining, flooring, heating, lighting, furniture, power, generator, insurance, permits and any site‑specific extras.
- Site visit report: Supplier must provide a signed risk assessment and ground‑condition note (see the Site Visit Checklist).
- Public liability insurance: Minimum £5 m cover; request a copy of the certificate.
- Health & safety documentation: Method statements for erection/dismantle, emergency procedures, and a copy of the supplier’s HSE registration (if applicable).
- Contract terms: Clear cancellation policy, deposit schedule, force‑majeure clause, and a defined “completion” point (e.g., hand‑over of keys or sign‑off sheet).
- References & accreditations: Check for membership of the National Association of Marquee Hire (NAMH) or Event Supplier & Services Association (ESSA).
- Sub‑contractor transparency: Confirm whether the supplier uses their own crew or subcontractors; if subcontractors, ensure they are covered by the same insurance.
Essential Questions to Ask Suppliers
- Can you provide a full, itemised written quote including all potential surcharges (ground plates, generator, access)?
- What is your exact erection and dismantle timeline on the event day?
- Do you carry out a penetrometer test on site, and will you share the results?
- What is your contingency plan if the weather forces a delay (e.g., high winds > 40 mph)?
- How do you handle damage to the venue’s ground or underground services?
- What is the process for signing off the completed structure (handover checklist, photos, sign‑off sheet)?
- Are there any hidden fees for late‑night dismantle or weekend collection?
- Can you supply a copy of your current public liability certificate and risk assessment template?
Post‑Event Rights
- Inspect the marquee and ancillary equipment before the supplier leaves; note any damage on the handover sheet.
- Report defects in writing within 48 hours; the supplier has 14 days to propose a remedy under the Consumer Rights Act.
- Retain all correspondence, photos, and the signed risk assessment for at least six years in case of a dispute.
Frequently Asked Questions
- Do I need a site visit for a small garden party?
- Yes. Even a 3 m × 3 m canopy must meet HSE wind‑load rules and the supplier must show £5M liability cover.
- What if the ground is unsuitable on the day?
- Reputable firms carry modular base plates and can switch to a ballasted system, but the cost rises – typically £100‑£150 extra.
- Can I supply my own generator?
- You can, yet the marquee company must certify the connection meets BS 7671. Most prefer to provide their own to keep the warranty intact.
- How long does a site visit take?
- Allow 45‑60 minutes for a standard 10 m × 20 m structure; larger clear‑spans may need two hours.